Bitmain ANTSPACE HD5 Hydro-Cooling Mining Container
The Bitmain ANTSPACE HD5 is an industrial hydro-cooling mining container designed for large-scale cryptocurrency mining operations. According to the supplied specifications, it supports up to 308 compatible hydro-cooled ASIC miners, with a normal power rating of 1,512 kW and a maximum power rating of 1,765 kW.
Designed for compatibility with the Antminer S19 Hyd, S21 Hyd, and S23 Hyd series, the ANTSPACE HD5 combines containerized mining infrastructure with an integrated dry-cooling tower and plate heat-exchange connections. Its liquid-cooling architecture is intended to manage heat generated by high-density mining equipment in professional mining facilities.
The supplied specifications state a PUE of 1.021 at 25°C ambient temperature and a dry-cooling tower heat dissipation capacity of 1,500 kW. The system uses a 400V ±5% electrical supply at 50/60Hz and includes four 1,200A main power distribution switches.
With its industrial electrical configuration, dedicated cooling connections, and support for up to 308 compatible miners, the ANTSPACE HD5 is designed for large mining farms, data centres, and professional hosting facilities.
Key Features
- Supports up to 308 compatible S19 Hyd, S21 Hyd, and S23 Hyd miners.
- 1,512 kW normal power rating and 1,765 kW maximum power rating.
- Hydro-cooling infrastructure for compatible liquid-cooled ASIC miners.
- Specified PUE of 1.021 at 25°C ambient temperature.
- Integrated dry-cooling tower with 1,500 kW stated heat dissipation capacity.
- DN100 dry-cooling tower and plate heat-exchange connections.
- 400V ±5% electrical input and 50/60Hz frequency compatibility.
- Containerized design for professional mining facilities.
ANTSPACE HD5 Technical Specifications
| Product | Bitmain ANTSPACE HD5 |
|---|---|
| Miner Capacity | 308 units |
| Compatible Miners | S23 Hyd, S21 Hyd, and S19 Hyd series |
| PUE | 1.021 at 25°C ambient temperature |
| Normal Power | 1,512 kW |
| Maximum Power | 1,765 kW |
| Container Dimensions | 12,192 × 2,438 × 2,896 mm |
| Container Certification | CSC |
| Shipping Weight | 11 tonnes |
| Operating Weight | 18 tonnes |
| Input Voltage | 400V ±5% |
| Input Frequency | 50/60Hz |
| Main Distribution Cabinet Switches | 1,200 A × 4 |
| Rated Current | 700 A × 4 |
| Rated Current per Miner | 10 A |
| Dry Cooling Tower Connection | DN100 (ISO2852 PN16) |
| Plate Heat Exchanger Connection | DN100 (GB/T 9122-2010 PN16) |
| Flow Rate 1 | 67.2 m³/h |
| Flow Rate 2 | 73.9 m³/h |
| ANTSPACE Units per 3,750 kVA Transformer | 2 |
Electrical and Cable Requirements
| Cable Material | Copper |
|---|---|
| Cable Voltage Rating | Above 600V |
| L1 Inlet Cable | 400 kcmil (185 mm²) × 8 single-core cables |
| L2 Inlet Cable | 400 kcmil (185 mm²) × 8 single-core cables |
| L3 Inlet Cable | 400 kcmil (185 mm²) × 8 single-core cables |
| Neutral Cable | 400 kcmil (185 mm²) × 4 single-core cables |
| Protective Earth Cable | 400 kcmil (185 mm²) × 4 single-core cables |
Dry Cooling Tower Specifications
| Model | EC2-DT Dry Cooler (Container Type) |
|---|---|
| Listed Equipment Dimensions | 2,000 × 1,130 × 2,360 mm |
| Additional Listed Size | 12,192 × 2,438 × 2,896 mm |
| Shipping Weight | 12 tonnes |
| Operating Weight | 14 tonnes |
| Heat Dissipation Capacity | 1,500 kW |
| Operating Power | ≤80 kW |
| Input Voltage | 400V ±5% |
| Input Frequency | 50/60Hz |
| Container Certification | CSC |
| Dry Cooler Connection | DN100 (ISO2852 PN16) |
| Drain Pipe Connection | DN25 (tapered tube) |
| Noise Level | 72 dB |
| Coolant Usage | 2.1 m³ |
Certifications and Safety Standards
- CSC container certification
- NFPA 79:2021
- UL 508A:2018 R8.21
- CSA C22.2 No. 14-18
- ANSI/ISO 12100:2012
- IEC 60204 Ed 5.1:2009
Installation Considerations
The ANTSPACE HD5 is industrial mining infrastructure and requires a suitably equipped installation site. Its 400V electrical input, high-current distribution system, large copper cable requirements, and dedicated cooling connections require professional engineering and installation.
Before deployment, buyers should confirm transformer capacity, electrical distribution, cable sizing, grounding, coolant circulation, cooling tower connections, drainage, and local regulatory requirements. Qualified electrical and cooling-system professionals should oversee installation.
Mine Your Wealth — Your Gateway to Cryptocurrency Mining.






Reviews
There are no reviews yet.